The NYCT Replacement of 6 Traction Elevators at 181st and 190th Street Stations on the 8th Avenue Line in Manhattan included new elevators, wider doors, and improved access between the lower mezzanine near the platforms and the upper mezzanines.

Project Details

  • Contract Value: $28.5M

  • Completion Date: December 2021

  • Location: Manhattan, NY

  • Scope of Work:

    • Replacement of six traction elevators at two stations, 181st Street and 190th Street Stations on the 8th Avenue Line

    • New concrete shaft walls, structural steel repairs and replacement, architectural finishes at elevator entrances

    • Improved access between the lower mezzanine near the platforms and the upper mezzanines

PHONE 631.589.8600

EMAIL info@fortecc.com

MAIN OFFICE

1770 Motor Parkway

Islandia, NY 11749

NEW YORK CITY OFFICE

385 5th Avenue

New York, NY 10016

Copyright © 2024 Forte Construction Corp.
Equal Opportunity Employer

Employee Webmail

  • Facebook
  • LinkedIn
  • Instagram
bottom of page