NYCT ADA Platform Edge Improvements at 34th St Herald Square
Location
Manhattan
Scope of Work
- Removed and replaced approximately 6,000 LF of platform edge concrete, rubbing board, and tactile warning strips
- Installed nearly 15,000 SF of granite tile along platform edges and at raised ADA areas
- Replaced all platform end gates
- Adjusted CCTV monitors as required
- Performed all work across 16 weekend G.O.s
- Completed the project ahead of schedule and with fewer Owner-provided services than originally anticipated
Station(s) & Subway Line(s)
34th St-Herald Sq Station - Serves the B/D/M/F Lines
The work included the removal and replacement of nearly 6000 LF of platform edge concrete, rubbing board & tactile; the installation of nearly 15,000 SF of granite tile along the platform edges and at the raised ADA areas; replacement of platform end gates; adjustment of CCTV monitors. The work was performed on 16 weekend G.O.s.